Skip to content

Robotic Workpiece Loading for Deep Hole Drilling Automation

A European spindle manufacturer runs a TBT ML250 deep hole drilling machine producing coolant holes in shafts 20–50 mm diameter, 75–550 mm long. Cycle times vary from 3 to 30 minutes, keeping one operator tied to the machine. The manufacturer implements a Halter LoadAssistant robot cell with double-sided gripper and 176-position grid plate storage. The robot loads four shafts at a time via buffer stations. Average loading cycle: 3.5 minutes. The cell runs one attended shift plus an unattended night shift, doubling production capacity without adding labour.

Why Automate Deep Hole Drilling Workpiece Loading?

Deep hole drilling presents specific challenges for manual loading:

ChallengeImpactAutomation Benefit
Long, varying cycle timesOperator idle time or absent during short cyclesRobot tends the machine continuously
Heavy workpiecesManual handling fatigue, injury riskRobot handles weight safely
Oil and coolant environmentSlippery floors, operator exposureRobot works in the environment
High-value partsScrap from handling damageConsistent, controlled handling
Multiple operations per partGundrill + ream + rifle (e.g., barrel cells)Robot transfers between machines

The primary motivation is typically not headcount reduction but machine utilisation improvement — ensuring the deep hole drilling machine runs during breaks, shift changes, and unattended periods.

Automation Methods

Comparison

MethodTypical PayloadWorkpiece LengthFlexibilityRelative CostBest For
6-axis robot cell10–200 kgUp to 1,000 mmHighHighMixed batches, multiple machines
Gantry loader50–500 kgUp to 3,000 mmLow–ModerateModerateHigh volume, long shafts
Walking beam / conveyor10–100 kgUp to 500 mmLowLowHigh volume, identical parts
Pallet changer100–1,000 kgUp to 2,000 mmLowModerateHeavy, large parts
Bar loader (automatic)Up to 500 kgUp to 6,000 mmVery lowLowBar stock, continuous production

Robot Cell (6-Axis)

The most flexible option. A 6-axis industrial robot (FANUC, KUKA, ABB, or similar) picks raw workpieces from a storage system, loads them into the deep hole drilling machine, and removes finished parts.

Key design elements:

  • Gripper — double-sided or quick-change gripper for raw/finished parts
  • Part storage — grid plates, pallets, or conveyor for raw and finished parts
  • Buffer stations — pre-staging positions to decouple robot and machine cycles
  • Safety system — light curtains, interlocks, and protective fencing
  • Controller integration — robot communicates with the drilling machine PLC

Gantry Loader

A gantry system spans the machine working area and transfers workpieces along a linear axis. Suitable for long, heavy shafts where a robot's reach is insufficient.

Key considerations:

  • Linear axis length must accommodate workpiece length plus clearance
  • Gripper travels above the machine, requiring headroom
  • Part storage is typically at one or both ends of the gantry

Integration with Existing Machines

Most deep hole drilling machines can be retrofitted for automated loading:

  1. Verify the machine has a standard interface for external loading (automatic chuck / steady rest open-close, cycle start signal)
  2. Install sensors to confirm workpiece presence and position before clamping
  3. Provide electrical and pneumatic connections for the gripper system
  4. Program the robot and machine controller handshake sequence
  5. Implement collision avoidance logic

Tip: The simplest retrofit path is to use the machine's existing M-code interface. Most deep hole drilling machines have spare M-functions that can control chuck open-close, steady rest retract, and cycle start. No machine control modification is needed — only the robot-to-machine handshake signals.

Cell Design Principles

Robot-to-Machine Handshake Sequence

  1. Machine completes cycle, spindle stops, tool retracts
  2. Robot signals "request load/unload"
  3. Machine confirms: spindle stopped, chuck open, steady rest retracted
  4. Robot removes finished part, places raw part
  5. Robot confirms: part seated, gripper clear
  6. Machine closes chuck, advances steady rest, starts cycle
  7. Robot moves finished part to output

Cycle Time Management

The most important design principle: decouple robot cycle time from machine cycle time.

If the robot must load and unload during machine idle time, the loading sequence is on the critical path. Strategies to minimise idle time:

StrategyHow It WorksIdle Time Reduction
Double gripperRobot carries raw part in one gripper, finished in other — swap in one motion50–70%
Buffer stagingRobot pre-stages raw parts at buffer stations while machine runs80–90%
Batch loadingRobot loads multiple parts into buffer, machine pulls them one by one90%+
Dual-station workholdingMachine has two spindles — robot loads one while the other cuts95%+

The Halter cell at Ott-Jakob uses buffer staging with four-part batch loading, achieving a 3.5-minute average load cycle with most of the loading happening while the machine is cutting.

Gripper Design

Workpiece TypeGripper TypeNotes
Cylindrical shafts (consistent OD)V-jaw gripper with serrated padsSelf-centering, accommodates diameter variation
Cylindrical shafts (varying OD)Three-jaw concentric gripperCentres the part regardless of diameter
Stepped shaftsCustom-contoured gripper fingersMatches the workpiece profile
Blind bore partsInternal expanding mandrelGrips from the bore
Finished surfacesSoft jaws or rubber padsProtects surface finish

Storage System Design

SystemCapacitySuitable For
Grid plate50–200 positionsShafts up to 600 mm, small to medium batches
Pallet stacker10–50 palletsLarger parts, mixed production
ConveyorContinuousHigh volume, single part family
Magazine / tube20–100 piecesBar stock, short parts

Case Studies

Case 1: Ott-Jakob / Halter — TBT ML250 Robot Cell

DetailDescription
MachineTBT ML250 deep hole drilling machine
WorkpieceSpindle coolant holes, 20–50 mm diameter, 75–550 mm long
RobotHalter LoadAssistant Universal Premium 35
Storage176-position + 88-position grid plates
GripperDouble-sided end effector with custom fingers
Loading strategy4-part batch with buffer stations
Load cycle3.5 minutes (being optimised)
ResultsOne attended shift + unattended shift, doubled capacity

Case 2: Mollart / FANUC — 3-Machine Barrel Cell

DetailDescription
Machines3 deep hole drilling machines
WorkpieceHydraulic transmission shafts, 384 mm deep holes
RobotFANUC M-20iD/25 on gantry rail
ControlFANUC Series 35i-Model B multi-path CNC
Result90%+ uptime efficiency, 0.2 mm positional accuracy

Case 3: TBT / Glumann — ML500 Automated Shaft Line

DetailDescription
MachineTBT ML500 with BTA/STS drilling
WorkpieceShafts 80–140 mm diameter, 500–2,000 mm long
LoadingTwo-level chain conveyor + two-armed gantry
ControlFully integrated into machine CNC
OperationOperator enters only length, diameter, and depth

Case 4: UNISIG — Flexible Automation Platform

DetailDescription
ApproachModular automation (robot, gantry, conveyor, pallet changer)
ApplicationsAerospace landing gear, rifle barrels, automotive shafts
IntegrationSingle supplier for machine + automation

ROI Analysis

Typical Costs

ComponentCost Range
6-axis robot cell (complete)£60,000–150,000
Gantry loader system£40,000–100,000
Conveyor / walking beam£15,000–40,000
Integration engineering£10,000–30,000
Safety system£5,000–20,000
Tooling / grippers£5,000–20,000
Total (typical robot cell)£80,000–250,000

Typical Savings

Saving SourceAnnual Value
Labour — one operator per shift£30,000–50,000
Labour — unattended shift (same operator runs 2 machines)£25,000–40,000
Machine utilisation increase (20–40% more cutting time)£15,000–50,000
Reduced handling damage / scrap£2,000–10,000

Payback Period

ScenarioTypical Payback
1 machine, 2 shifts, robot replaces 1 operator18–30 months
1 machine, 3 shifts (lights-out), robot enables +1 shift12–18 months
2 machines, 1 robot tending both10–16 months
3+ machines, automated transfer line8–14 months

Warning: Do not underestimate the cost of integration and commissioning. The robot hardware is typically 40–50% of the total project cost. Programming, sensors, safety system, and commissioning account for the remaining 50–60%. A £100,000 robot may represent a £200,000+ total project.

Implementation Challenges

ChallengeImpactMitigation
Workpiece variationGripper design complexityUse adjustable or quick-change grippers
Coolant / chip environmentSensor contamination, gripper slipUse sealed sensors, textured gripper pads
Machine interface compatibilityCommunication failuresUse standard fieldbus (Profinet, EtherCAT)
Collision risk during loadingMachine damage, part scrapRedundant position sensors, force monitoring
Cycle time matchingMachine idle waiting for robotBuffer staging, double gripper
Long setup for batch changesRobot reprogramming timeOffline programming, quick-change gripper
Safety validationDelayed commissioningEngage safety integrator early
Operator acceptanceResistance to automationInvolve operators in design, training programme

Troubleshooting

ProblemLikely CauseCorrection
Robot cannot pick part repeatablyStorage position tolerance too looseCalibrate storage positions, use vision or force sensing
Gripper slips on oily workpieceGripper pad material wrongReplace pads with high-friction material (urethane, ceramic)
Machine waits for robot at cycle startBuffer stations emptyVerify robot scheduling logic, increase buffer size
Robot crashes into machine during loadPosition offset after maintenanceRe-teach loading positions after any machine alignment work
Part not seated in chuckChip on locating surfaceAdd air blow-off at loading station
Scratches on finished boreGripper damageInspect gripper pads, replace if worn
Robot stops with no errorSafety interlock trippedCheck all safety gates, light curtains, and emergency stops
Communication timeoutPLC handshake signal lostCheck fieldbus connection, verify signal timing

FAQ

Why automate workpiece loading for deep hole drilling?

The primary benefit is machine utilisation — automated loading enables unattended operation during breaks, shift changes, and night shifts, increasing cutting time by 30–100%.

What automation options are available for deep hole drilling?

Robot cells (most flexible), gantry loaders (long shafts), walking beam conveyors (high volume), pallet changers (heavy parts), and bar loaders (bar stock).

Can existing deep hole drilling machines be retrofitted for robotic loading?

Yes — most machines can be retrofitted using spare M-code interfaces for chuck open-close, steady rest retract, and cycle start. No machine control modification is typically needed.

How long does it take to implement a robot loading cell?

Typical project timeline: 12–20 weeks from order to production. Design 4–6 weeks, build 6–8 weeks, integration and commissioning 2–6 weeks.

How much does a robot loading cell cost for a deep hole drilling machine?

Total project cost (robot, safety system, integration, tooling): £80,000–250,000. The robot itself is 40–50% of this.

What is the typical payback period?

12–30 months depending on the number of shifts and utilisation improvement. Multi-machine cells pay back faster than single-machine cells.

Can one robot tend multiple deep hole drilling machines?

Yes — robots mounted on gantry rails can serve 2–4 machines. The Mollart/FANUC cell demonstrates this configuration with 3 machines.

What gripper type is best for cylindrical shafts?

Double-sided V-jaw grippers with serrated or urethane pads are standard for shafts. The double-sided design allows the robot to pick a raw part and remove a finished part in one motion.

How does the robot and machine communicate?

Typically through digital I/O handshake signals or fieldbus (Profinet, EtherCAT). The robot requests load/unload, the machine confirms safe state, the robot loads, and the machine starts.

Is unattended (lights-out) deep hole drilling feasible with robotic loading?

Yes — the Ott-Jakob cell at TBT runs unattended shifts regularly. Requirements: reliable chip evacuation, tool monitoring, coolant level monitoring, and collision detection.

Summary

Robotic and automated workpiece loading for deep hole drilling machines is a proven technology that delivers substantial productivity gains:

  • Methods — 6-axis robot cells (most flexible), gantry loaders (long shafts), walking beam conveyors (high volume), pallet changers (heavy parts)
  • Cell design — double grippers, buffer staging, and batch loading minimise machine idle time
  • Integration — most machines can be retrofitted via spare M-code interfaces without control modification
  • ROI — 12–30 month payback typical; multi-machine cells pay back faster
  • Unattended operation — proven in production, requires reliable chip evacuation and tool monitoring
  • The spindle manufacturer in the opening scenario doubled production capacity by adding a robot cell that runs one attended shift plus one unattended night shift, without adding labour

Deep Hole Drilling Hub — Your Trusted Third-Party Industry Resource