Skip to content

Deep Hole Drilling: Economics, Cost Optimisation, Selection

A manufacturer of hydraulic cylinders switched from gun drilling to BTA drilling for a 50 mm diameter bore in a 2,000 mm long cylinder. The tooling cost increased by 40% per station. The cycle time dropped from 45 minutes to 12 minutes. The per-part cost fell by 55%. A manufacturer of fuel injector bodies switched from twist drilling to gun drilling for a 4 mm diameter × 200 mm long oil return bore. The tooling cost increased by 300% per hole. The reject rate dropped from 18% to 0.5%. The per-part cost fell by 35%. Both decisions were correct. Both decisions required understanding not just the cost of the tool and the machine time, but the total cost of producing a conforming hole — including scrap, rework, inspection, and the hidden cost of unreliable chip evacuation at depth. Deep hole drilling economics is not about choosing the cheapest tool or the fastest cycle. It is about matching the process to the geometry, material, tolerance, and volume of the hole to minimise the total cost per good part.

Cost Structure of Deep Hole Drilling

The total cost of a deep drilled hole consists of five components:

Cost Components

ComponentTypical ShareNotes
Machine time (labour + depreciation)40–60%Dominant for long cycle times
Tooling (drill + inserts per hole)15–25%Highly variable by material and diameter
Coolant and filtration5–10%High-pressure systems are expensive to operate
Setup and alignment5–15%Amortised over batch size
Scrap, rework, and inspection5–20%Often underestimated

The Non-Linear Depth Cost

The most important concept in deep hole drilling economics: cost does not scale linearly with depth.

L/D RatioRelative Cost per mm of DepthReason
≤ 10:11.0× (baseline)Conventional twist drilling possible
10:1–30:11.5–2.0×Specialised tooling, coolant-through required
30:1–50:12.0–4.0×Chip evacuation becomes unreliable
50:1–80:14.0–8.0×Step drilling or peck cycles required
80:1–150:18.0–20×Specialised process, high scrap risk

The non-linearity arises from three factors:

  1. Chip evacuation — at L/D > 30:1, chip friction against the bore wall increases exponentially, requiring higher coolant pressure and more frequent peck cycles
  2. Tool deflection — the drill shank torsional wind-up at depth reduces the effective feed at the cutting edge, requiring speed/feed adjustments
  3. Failure consequence — a tool breakage at 80:1 depth scraps the component; at 10:1 depth it is recoverable

Comparative Economics by Drilling Method

Cost Comparison: Gun Drilling vs. BTA Drilling vs. Trepanning

FactorGun DrillingBTA DrillingTrepanning
Diameter range1–50 mm18–300 mm50–1,000 mm
Relative tool cost (per hole)MediumHighVery high
Material removal rateLowHigh (3× gun drilling)Medium
Surface finish (as-drilled)Ra 0.4–0.8 µmRa 0.8–3.2 µmRa 1.6–6.3 µm
Typical toleranceH8–H9H9–H11H11–H12
Scrap risk (at L/D > 50:1)ModerateLowLow
Setup costLow-moderateModerateHigh
Break-even batch size1–50050–10,0001–100
Secondary finishingOften not neededOften required (hone/skive)Always required
Machine cost€100k–€500k€300k–€1,000k€500k–€2,000k

Cost per Hole by Diameter (Estimates for Steel, L/D = 20:1)

DiameterGun DrillingBTA DrillingTrepanning
10 mm × 200 mm€3–€8N/AN/A
25 mm × 500 mm€12–€25€10–€20N/A
50 mm × 1,000 mm€30–€60€15–€30€25–€50
100 mm × 2,000 mmN/A€40–€80€50–€100
200 mm × 3,000 mmN/A€100–€200€120–€250

These are order-of-magnitude estimates. Actual costs depend on material, tolerance, surface finish requirements, and batch size.

Process Selection Guide

Decision Matrix

Primary CriteriaGun DrillingBTA / STSTrepanningEjector (Double-Tube)
Diameter ≤ 20 mm✔ Best choiceNot suitableNot suitableNot suitable
Diameter 20–50 mm✔ Good✔ GoodNot suitable✔ Good
Diameter 50–150 mmNot suitable✔ Best choice✔ Good✔ Best choice
Diameter > 150 mmNot suitable✔ Good✔ Best choice✔ Good
L/D ≤ 10:1OverkillOverkillOverkill✔ Good
L/D 10:1–50:1✔ Good✔ Good✔ Good✔ Best choice
L/D 50:1–100:1✔ Best choice✔ GoodFair✔ Good
L/D > 100:1✔ Best choiceFairNot suitableFair
Tolerance H7–H8✔ Best choiceModerateNot suitableModerate
Tolerance H9–H11✔ Good✔ GoodFair✔ Good
Batch < 100✔ Best choiceFairFairFair
Batch 100–1,000✔ Good✔ Best choiceFair✔ Good
Batch > 1,000Moderate✔ Best choiceModerate✔ Best choice

Material Cost Multipliers

Different materials require different cutting speeds, feed rates, and tool grades — all of which affect cost:

MaterialRelative MachinabilitySpeed vs. SteelTool Life vs. SteelCost Multiplier vs. Mild Steel
Mild steel (C45, 1020)Excellent1.0×1.0×1.0× (baseline)
Alloy steel (4140, 42CrMo4, 300 HB)Good0.7–0.8×0.5–0.7×1.2–1.5×
Tool steel (D2, H13, 250 HB)Fair0.5–0.6×0.3–0.5×1.5–2.0×
Stainless steel (304, 316)Fair0.5–0.7×0.3–0.5×1.5–2.0×
Titanium (Ti-6Al-4V)Fair-poor0.3–0.5×0.2–0.4×2.0–3.0×
Inconel 718 (annealed)Poor0.2–0.3×0.1–0.2×3.0–5.0×
Inconel 718 (40 HRC)Very poor0.15–0.25×0.02–0.10×5.0–10×

Cost Optimisation Strategies

Speed-Feed Optimisation

The relationship between cutting speed, feed, tool life, and cost is not linear — there is an economic optimum that balances tooling cost against machine time:

ParameterEffect on Tool LifeEffect on Cycle TimeEffect on Cost
Increase cutting speed 20%Decrease tool life 40–60%Decrease cycle time 17%Variable — often increases total cost
Increase feed 20%Decrease tool life 15–25%Decrease cycle time 17%Often reduces total cost
Both increased 10% eachDecrease tool life 30–40%Decrease cycle time 17%Usually increases cost
Optimise speed for max tool lifeIncrease 2–5×Increase 20–50%Lower cost at small batch sizes

Rule of thumb: For production deep hole drilling, the economic optimum is typically at a cutting speed 20–30% below the maximum recommended speed and a feed 10–20% above the minimum recommended feed.

Tool Life Management

StrategyEffect on Per-Hole CostBest For
Replace tool at fixed interval (before end of life)+5–15% tool cost, −50–80% scrapCritical components, expensive materials
Run to failure (minimum tool changes)Lowest tool cost, highest scrapLow-volume, cheap materials
Regrind vs. replace−30–50% per regrind (3–5 regrinds possible)Gun drills > 6 mm diameter
Indexable inserts (BTA)+10–20% per edge, −50% change timeHigh-volume BTA drilling

Coolant Cost Management

StrategySavingTrade-off
Optimise pressure to minimum required−10–30% pump energyRisk of chip packing at marginal pressure
Fine filtration (≤ 20 µm)−20–40% tool wearHigher filter element cost
Temperature control (20–30°C)−10–20% tool wear variationChiller capital cost
Coolant life extension (centrifuge)−30–50% coolant purchasesCentrifuge capital cost

Investment Decision Framework

When to Upgrade from Gun Drilling to BTA

IndicatorThreshold
Bore diameter> 25 mm
Annual volume> 500 parts
Current cycle time vs. targetCurrent > 2× target
Scrap rate> 5% from gun drilling issues
Available machine utilisation> 70%

Payback Calculation Example

Converting a hydraulic cylinder bore from gun drilling to BTA drilling:

ItemGun DrillingBTA Drilling
Bore diameter50 mm50 mm
Bore length1,500 mm1,500 mm
Cycle time (including handling)35 minutes10 minutes
Tool cost per hole€4€6
Scrap rate4%1%
Machine rate€80/hour€80/hour
Cost per good part€52.30€16.50

Investment: BTA machine — €450,000 (or €50,000 BTA conversion kit) Savings per part: €35.80 Annual volume: 3,000 parts Annual savings: €107,400 Payback period: 4.2 years (full machine) / 5.6 months (conversion kit)

When to Choose Trepanning

Trepanning is economically justified when:

  1. Bore diameter exceeds 50 mm — the core removed is valuable material
  2. Core material can be reused — a 150 mm core from a 300 mm bore × 2,000 mm length weighs approximately 110 kg in steel — worth €100–€300 in material alone
  3. Cutting forces must be minimised — trepanning removes only 30–40% of the cross-sectional area vs. 100% for solid drilling
  4. Available machine power is limited — lower cutting forces allow smaller machines

Case Studies

Case 1: Hydraulic Cylinder — Gun Drilling to BTA

BeforeAfterImprovement
Gun drilling, 50 mm × 1,500 mmBTA drilling−55% cost per hole
35 min cycle10 min cycle−71% cycle time
4% scrap1% scrap−75% scrap
200 holes per regrind500 holes per insert edge+150% tool life

Key insight: The BTA method's internal chip evacuation eliminated the chip packing that caused most of the gun drilling scrap.

Case 2: Fuel Injector Body — Twist Drill to Gun Drill

BeforeAfterImprovement
Twist drill, 4 mm × 200 mmGun drilling−35% cost per hole
18% reject rate0.5% reject rate−97% rejects
3 min cycle4 min cycle+33% cycle time
No straightness control±0.01 mm straightnessPredictable quality

Key insight: The higher cycle time was more than offset by the elimination of scrap and rework.

Case 3: Military Component — Gun Drilling to Double-Tube BTA

Reported in Cutting Tool Engineering: a military contractor switched from gun drilling to a double-tube BTA system.

ItemBeforeAfter
Per-part cost$33$15
Investment$20,000 (conversion)
Payback period21 days
Annual savings$75,000

Case 4: Nuclear Steam Generator Tube Sheet — Single-Spindle to Multi-Spindle

BeforeAfterImprovement
Single-spindle BTA4-spindle BTA−60% total drilling time
8,000 holes, 45 s each8,000 holes, 45 s each (×4)90 hours → 22.5 hours
4 machines required1 machine required−75% capital

Key insight: Multi-spindle drilling requires higher initial investment but delivers the lowest per-hole cost for very large hole quantities (> 5,000 holes per tube sheet).

FAQ

Q: What percentage of deep hole drilling cost is machine time? 40–60% in most production environments. Tooling accounts for 15–25%, coolant 5–10%, setup 5–15%, and scrap/rework 5–20%. Machine time dominates because deep hole drilling is inherently slow — cutting speeds are low and feed rates are constrained by chip evacuation.

Q: How does L/D ratio affect cost? Non-linearly. A hole with L/D = 50 costs 2–4× more per mm of depth than L/D = 10. At L/D > 80:1, the cost per mm can be 8–20× higher because of chip evacuation problems, tool deflection, and the catastrophic cost of a tool breakage.

Q: When should I choose gun drilling over BTA drilling? Gun drilling is the best choice for: diameters below 20 mm, L/D ratios above 80:1, tight tolerances (H8 or better), small batch sizes (< 100), and materials that are difficult to machine with multi-edge tools.

Q: When is BTA drilling more economical? BTA drilling is more economical for: diameters above 25 mm, medium to high volumes (> 500 parts/year), when internal chip evacuation improves process reliability, and when the higher material removal rate (3× gun drilling) can reduce cycle time.

Q: What is trepanning and when is it economical? Trepanning cuts a ring-shaped groove around a solid core, leaving the core intact for reuse. It is economical for bores > 50 mm diameter where the core material is valuable, when cutting forces must be minimised, or when available machine power is limited.

Q: What is the most effective cost reduction strategy in deep hole drilling? Eliminating scrap caused by chip evacuation problems. A 5% scrap rate adds 5.3% to the cost of every good part. A 15% scrap rate (common in difficult materials) adds 17.6%. Improving chip control through method selection, coolant optimisation, and chip breaker geometry typically delivers the largest single cost reduction.

Q: How does material selection affect deep hole drilling cost? Material is the second-largest cost driver after L/D ratio. Inconel 718 at 40 HRC costs 5–10× more per hole than mild steel. Titanium costs 2–3× more. The cost multiplier comes from lower cutting speeds, shorter tool life, higher coolant pressure requirements, and higher scrap risk.

Q: What batch size justifies a dedicated deep hole drilling machine? A dedicated gun drilling machine (€100k–€300k) is typically justified at 500–2,000 parts/year for small-diameter work. A BTA machine (€300k–€1,000k) is justified at 1,000–5,000 parts/year for larger diameters. Contract drilling services are more economical below these volumes.

Q: Can a multi-spindle machine reduce per-hole cost? Yes, for large quantities of identical holes. A 4-spindle BTA machine can reduce drilling time by 75% compared to a single-spindle machine. The breakeven is typically at 5,000+ holes per tube sheet or 10,000+ parts per year.

Q: What is the most common economic mistake in deep hole drilling? Choosing a process based on cycle time alone without considering scrap rate and tooling cost. A fast process with 10% scrap is usually more expensive than a slower process with 0.5% scrap. The total cost per good part — not the cycle time — is the correct economic metric.

Deep Hole Drilling Hub — Your Trusted Third-Party Industry Resource