Skip to content

Deep Hole Drilling Machine Foundation Re-Leveling and Grouting Procedure

A deep hole drilling machine that is out of level by 0.05 mm per meter produces holes that are out of straightness by 0.05 mm per meter of hole depth — a direct, one-to-one error. No amount of programming compensation, tool adjustment, or parameter optimization can correct a hole straightness problem caused by a machine that has settled out of level. The only fix is to re-level the machine and restore the foundation grout.

When Re-Leveling Is Needed

Symptoms of an Out-of-Level Machine

SymptomWhat It IndicatesHow to Verify
Hole straightness deviation — consistent curve in one directionMachine axis not parallel to gravitational referenceMeasure level on machine ways — check with precision level
Uneven guide bushing wear — one side worn moreMachine not level — bushing axis not aligned to drill axisMeasure guide bushing bore position relative to spindle
Spindle-to-guide bushing misalignment — vertical or horizontalMachine sag or settlement — foundation movementDial indicator — spindle to bushing alignment check
Way cover damage on one sideMachine twist — way covers bindingVisual — measure way gap on both sides
Cutting tool life variation between machinesDifferent level conditions cause different tool loadingCompare tool life data across machines
Vibration that changes with machine positionFoundation shifted — machine no longer sitting evenly on groutVibration analysis — compare before and after
Coolant pooling on one side of machineMachine tilted — coolant not draining to returnVisual — level check
Machine anchor bolts loose — repeatedlyFoundation movement — grout deteriorationTorque check — observe if bolts loosen after re-torquing
Check TypeFrequencyMethodAcceptance Criteria
Quick level check — operatorMonthlyPrecision level on main ways< 0.02 mm/m change from baseline
Full level check — maintenanceQuarterlyPrecision level on ways and cross-axisAll axes within 0.02 mm/m of level or manufacturer spec
Comprehensive geometry checkAnnuallyFull alignment — level — straightness — squarenessAll geometric tolerances per machine spec
After major eventImmediately afterFull level checkEarthquake — flood — machine crash — relocation

Level Measurement Methods

MethodAccuracyEquipment CostSkill RequiredBest For
Precision machinist level± 0.02 mm/m per divisionModerate ($200–$800)Moderate — reading and interpreting bubbleDaily — quick checks — standard accuracy
Electronic level / inclinometer± 0.005 mm/mHigh ($1,000–$5,000)Moderate — zero settingHigh-precision leveling — data logging
Laser level (rotary)± 0.05 mm/mModerate ($500–$2,000)Low — basic operationRough leveling — general reference
Laser tracker± 0.001 mm/mVery high ($50,000+)Very high — specialized trainingFull machine geometry — alignment — precision
Alignment telescope± 0.01 mm/mHigh ($3,000–$8,000)High — optical alignmentSpindle-to-bushing alignment — straightness
Dial indicator + straightedge± 0.01 mm/mLow ($100–$500)Moderate — setup and readingWay straightness — local level reference
Water level (manometer)± 0.1 mm/mLow ($50–$200)Low — basic operationLarge machines — no line of sight needed

Grout Types

Grout Comparison

Grout TypeCompressive Strength (MPa)Temperature RangeChemical ResistanceCure Time (to load)Best For
Cementitious (non-shrink)40–70 MPa-10 to 80°CPoor — water absorbs coolant3–7 daysGeneral — low cost — standard foundations
Epoxy grout80–120 MPa-20 to 100°CExcellent — coolant resistant24–48 hoursHigh-load machines — coolant exposure — precision
Polymer grout60–90 MPa-20 to 120°CGood — chemical resistant12–24 hoursModerate loads — faster cure
Polyester grout70–100 MPa-10 to 80°CGood — limited chemical resistance6–12 hoursRapid cure needed — temporary repair
Chock-fast grout (pourable)80–110 MPa-20 to 100°CExcellent24–48 hoursPermanent chocking — precision fit
Hydraulic cement30–50 MPa-10 to 60°CPoor4–8 hoursFast emergency repair — temporary

Grout Selection Criteria

CriterionCementitiousEpoxyPolymer
Machine weight — light (< 5 tons)
Machine weight — medium (5–20 tons)
Machine weight — heavy (> 20 tons)
Operating temperature < 60°C
Operating temperature 60–100°C
Coolant exposure — continuous
Oil exposure — continuous
Vibration — high
Cure time available < 24 hours
Cure time available 24–72 hours
Cost — lowestBestHigherModerate
Surface preparation requiredModerateCritical — must be clean and dryModerate

Re-Leveling Procedure

Preparation

StepActionDetail
1Measure and document current levelRecord level readings on all ways and cross-axes — date — machine condition (cold vs warm)
2Measure current alignmentSpindle to guide bushing — parallelism — squareness — document baseline
3Identify anchor bolt conditionCheck for rust — corrosion — thread damage
4Clear machine areaRemove tooling — coolant — chips — auxiliary equipment if needed
5Disconnect utilitiesCoolant lines — electrical — compressed air — hydraulic — mark all connections
6Support machine per manufacturer pointsUse machine jacking points — never lift from way surfaces or spindle
7Remove existing groutChip out deteriorated grout — expose foundation surface
8Prepare foundation surfaceClean — chip to rough surface — remove oil — dry thoroughly
9Build form around machine baseTight — leak-proof — grout dam — allow for proper venting
10Position leveling wedges or jacksAt each anchor bolt location — plus mid-points for long machines

Leveling Adjustment

StepActionDetail
1Place precision level on reference wayLongitudinal direction — clean way surface — allow temperature stabilization
2Zero level or record baseline readingConfirm level is calibrated
3Adjust machine height at each jacking pointTighten or loosen jacking bolts — 1/4 turn at a time — allow settling between adjustments
4Check level — longitudinalRead level — adjust — recheck — iterate until within spec
5Check level — transverse (cross-axis)Level across machine ways — adjust opposite side jacks
6Recheck longitudinal after transverse adjustmentCross-axis adjustment affects longitudinal — iterate
7Check twist (diagonal level)Place level diagonally across machine — check for twist
8Check all jacking points for uniform contactAll points should carry load — loose points indicate incorrect adjustment
9Final level readingDocument — all directions within spec
10Tighten anchor bolts — finger tight onlyDo not fully torque — grout must cure first

Grouting Procedure

StepActionDetail
1Verify form is tight and sealedNo leaks — grout dams at all openings — vent holes at high points
2Prime foundation surfacePer grout manufacturer — epoxy primer for epoxy grout — water for cementitious
3Mix grout per manufacturerExact water ratio for cementitious — exact resin/hardener ratio for epoxy — temperature matters
4Pour grout from one side onlyContinuous pour — no air entrapment — push air ahead of grout — use vent holes
5Maintain constant headKeep grout flowing — do not interrupt pour — have sufficient mixed grout ready
6Vibrate or rod groutRemove entrapped air — ensure complete fill under base — do not over-vibrate
7Check for complete fillGrout appears at all vent holes — no voids — level surface
8Allow initial setPer manufacturer — typically 30–60 minutes before finishing
9Finish exposed surfaceTrowel smooth — chamfer edges — remove excess
10Cure per manufacturerCementitious: keep wet 3–7 days (wet burlap + plastic). Epoxy: dry cure 24–48 hours at 20°C+

Post-Cure

StepActionDetail
1Verify cure time completedPer manufacturer — minimum cure before applying any load
2Check grout conditionNo cracks — no voids — no bond failure — full contact
3Sound test groutTap with hammer — solid sound = good bond — hollow sound = void
4Remove leveling jacks or wedgesIf non-load-bearing — fill voids with grout
5Torque anchor bolts to specificationCross-bolt pattern — final torque per manufacturer — typically 70–80% of bolt yield
6Recheck levelAfter anchor bolt torquing — verify level has not changed
7Reconnect utilitiesCoolant — electrical — air — hydraulic — per connection procedure
8Run machine without cutting30–60 minutes at operating speed — check for vibration — temperature
9Full level and alignment checkAfter thermal stabilization — verify level maintained
10Recheck anchor bolt torqueAfter 24 hours of operation — retorque if needed
11DocumentationFull report — before and after level readings — grout type — date — technician

Acceptance Criteria

ParameterAcceptance CriteriaMeasurement MethodFrequency of Verification
Machine level — longitudinal (along ways)< 0.02 mm/m or per manufacturer specPrecision level on reference wayAfter leveling — after grout cure — after 24 hours operation
Machine level — transverse (across ways)< 0.02 mm/m or per manufacturer specPrecision level on transverse surfaceAfter leveling — after grout cure
Machine twist< 0.02 mm/m difference between cornersLevel at four corners of machine baseAfter leveling — after grout cure
Way straightness — vertical plane< 0.01 mm/mPrecision straightedge + feeler gaugeAfter re-leveling — annually
Way straightness — horizontal plane< 0.01 mm/mDial indicator on wire or laserAfter re-leveling — annually
Spindle-to-guideway parallelism< 0.005 mm per 100 mmDial indicator on test bar vs wayAfter re-leveling — after thermal stabilization
Grout bond — no voids100% contact — no hollow sound on tappingSound test — tap with hammerAfter grout cure
Anchor bolt torquePer manufacturer specification ± 5%Torque wrenchAfter grout cure — after 24 hours operation

Grout Inspection and Maintenance

InspectionFrequencyMethodAcceptance Criteria
Visual grout inspectionQuarterlyLook for cracks — spalling — separation from machine baseNo cracks > 0.1 mm — no separation — no spalling
Sound testAnnuallyTap grout surface with hammer — listen for hollow soundSolid sound across entire grout area
Level checkQuarterlyPrecision level on reference ways< 0.02 mm/m change from baseline
Anchor bolt torque checkAnnuallyTorque wrench — verify torqueWithin 5% of specification
Edge conditionAnnuallyVisual — check grout edge for deteriorationNo crumbling — no erosion — no coolant staining
Crack monitoringQuarterlyMeasure any existing cracks — document changesNo progressive crack growth — no new cracks

FAQ

When does a deep hole drilling machine need re-leveling?

A deep hole drilling machine needs re-leveling when: the precision level shows more than 0.02 mm/m change from the baseline reading taken at installation or the last leveling (the foundation settles over time — especially on new foundations in the first 1–2 years — annual level checks detect this). Holes show a consistent straightness deviation in one direction (if every hole curves the same way, the machine axis is not level — the drill follows gravity — the hole curves). Uneven way wear is detected (one side of the ways wears faster than the other — indicating the machine is twisted or not level — the carriage rides heavier on one side). Guide bushing or tool life shows a left-right bias (one side of the bushing or drill wears faster — the misalignment caused by settlement puts uneven load on the tool). The machine experienced a foundation event (earthquake, flood, nearby excavation, or heavy impact — any of these can shift the foundation). Grout is visibly cracked or separated from the machine base (deteriorated grout means the machine is not fully supported — load is concentrated on anchor bolts and high spots).

How do I check if my deep hole drilling machine is level?

Use a precision machinist level (graduated to 0.02 mm/m — also called a 0.0005" per foot level). Place the level on a clean, dry reference way surface — the machine ways are the reference surface. Read the bubble position — center the bubble between lines. Check in two directions: longitudinal (along the machine ways — the direction of drilling feed) and transverse (across the ways — perpendicular to the drilling direction). Also check twist — place the level diagonally across the machine base. Record the readings at each location. Repeat in the same locations each time for trend data. The acceptance criteria for deep hole drilling machines is typically < 0.02 mm/m (0.001" per foot) in all directions — but always verify the manufacturer's specification, as some machines have tighter requirements. For quarterly checks, use the same level in the same location at the same machine temperature (cold — before startup) for consistent comparative data.

What type of grout should I use for a deep hole drilling machine foundation?

Epoxy grout is recommended for deep hole drilling machine foundations: high compressive strength (80–120 MPa — handles the dynamic loads from deep hole drilling), excellent chemical resistance (resists coolant and oil exposure that would deteriorate cementitious grout), good vibration damping (reduced transmission of drilling forces to the foundation), and moderate cure time (24–48 hours before applying full load — faster than cementitious). Cementitious grout can be used for light machines (< 5 tons) in dry areas where coolant exposure is minimal — but it absorbs coolant (causing degradation), has lower compressive strength (40–70 MPa), and requires 3–7 days cure. Polymer grout is an alternative for moderate loads when faster cure is needed (12–24 hours). For machines exposed to hot coolant (> 60°C), epoxy or polymer grout is mandatory — cementitious grout degrades at elevated temperatures. The added cost of epoxy grout (approximately 3–5× cementitious) is justified by longer service life (15–20 years vs 5–10 years for cementitious).

How long does foundation grout need to cure before operating the machine?

Cure time depends on grout type: epoxy grout — 24–48 hours at 20°C minimum (do not apply load until full cure — check manufacturer specification — lower temperature = longer cure time — below 10°C, epoxy may not cure at all). Cementitious grout — 3–7 days (keep wet during cure — apply wet burlap and plastic — the full 7-day cure provides maximum strength — at 3 days, approximately 70% of ultimate strength — light operation may be possible with manufacturer approval). Polymer grout — 12–24 hours (faster cure than epoxy — check manufacturer for specific cure schedule). During cure: do not apply machine load (no machine weight on anchor bolts — no cutting forces), do not torque anchor bolts to full specification (finger tight only during grouting — torque after cure), do not connect utilities that could cause vibration, and maintain proper temperature (follow grout manufacturer's temperature range — typically 15–30°C for most grouts). After cure: torque anchor bolts — reconnect utilities — run machine without cutting for 30–60 minutes — then check level again before production.

How often should machine level and grout condition be checked?

Check level quarterly — use a precision level on the reference ways — record readings in the same location each time — trend the data — if the trend shows progressive change, investigate before the deviation exceeds the limit. Check grout condition quarterly — visual inspection for cracks, spalling, separation, and edge deterioration — tap with a hammer annually to check for voids (hollow sound indicates bond failure). Check anchor bolt torque annually — verify all bolts are at specification. Perform a comprehensive geometry check annually — full alignment including spindle-to-guideway parallelism, way straightness, and squareness. Perform an immediate level check after any significant event — machine crash, earthquake, flood, nearby heavy excavation, or machine relocation. The annual comprehensive check is the most important — it catches problems that the quarterly level check might miss (like a localized foundation settlement under one corner that does not affect the overall level but does affect machine geometry).


Foundation re-leveling and grouting is a major maintenance operation that restores a deep hole drilling machine's geometric accuracy. Check level quarterly and grout condition visually — re-level when the level reading exceeds 0.02 mm/m change from baseline or when holes show consistent straightness deviation. Use epoxy grout for best chemical resistance and long service life. Follow the full procedure — preparation, leveling, grout pouring, cure, post-cure torque, and verification. A level machine produces straight holes. A machine that has settled out of level produces scrap — no amount of programming or tool adjustment can fix a foundation problem. This article reflects industry practice as of 2026.

Deep Hole Drilling Hub — Your Trusted Third-Party Industry Resource