Deep Hole Drilling Machine Relocation and Rigging Guide

A BTA machine weighs 15–40 tons and requires precision realignment within 0.02 mm/m. Professional rigging costs $8,000–25,000. Attempting to save money with unqualified riggers costs more in damage and downtime.

Relocation Planning Timeline

PhaseTimelineKey Activities
Assessment4–6 weeks before moveMachine survey, transport route survey, rigging method selection
Contractor selection3–4 weeks before moveGet 3 quotes, verify insurance, check references
Preparation2–3 weeks before moveDrain coolant, disconnect utilities, label connections
Rigging and loading1–2 daysCrane hire, rigging, securing for transport
TransportVariableFlatbed or low-boy trailer, permits, escort vehicles
Unloading and placement1–2 daysCrane hire, positioning on foundation
Reassembly and alignment3–10 daysLevel, align spindle, align guideway
Re-commissioning2–5 daysCoolant fill, electrical check, test cut

Contractor Selection

Rigging Contractor Requirements

RequirementWhy It Matters
Experience with machine tools (not just general rigging)Machine tools require precision handling, not just lifting
Insurance: minimum $2 million liability + riggers liabilityCovers damage during the move
References from similar-size machine movesVerifies capability
In-house engineering for lift planComplex lifts require engineered plans
CNC machine transport experienceKnowledge of axis locking, way protection

Tip: Ask potential contractors: "How many deep hole drilling machines have you moved?" If the answer is zero, look elsewhere.

Questions to Ask Rigging Contractors

  1. What is your experience with machines over 15 tons?
  2. Do you have experience with long-bed machines (over 6 m)?
  3. How do you protect precision way surfaces during transport?
  4. Do you provide laser alignment after placement?
  5. What is your insurance deductible?

Pre-Move Preparation

Machine Preparation

  • [ ] Back up all CNC parameters, programs, and compensations
  • [ ] Mark and label all electrical, coolant, and hydraulic connections
  • [ ] Drain coolant system completely — including lines and pump
  • [ ] Drain hydraulic oil or seal all openings
  • [ ] Lock all axes with shipping brackets (manufacturer's procedure)
  • [ ] Remove or secure all protruding components (chip conveyor, coolant arm)
  • [ ] Wrap and protect way covers, ball screws, and linear guides
  • [ ] Take photographs of the machine in its current position for reference

Documentation to Prepare

  • Machine serial number and model
  • Original installation drawings and foundation plan
  • Electrical schematics
  • Coolant system diagram
  • Weight distribution data (axle loads for transport)
  • Rigging points specified by manufacturer

Transport Considerations

Transport Method Selection

Machine SizeRecommended TransportTypical Cost
Small gun drilling (< 5 tons)Flatbed truck$1,500–3,000
Medium BTA (5–15 tons)Step deck trailer$3,000–6,000
Large BTA (15–40 tons)Low-boy trailer$5,000–12,000
Extra long (> 10 m bed)Extendable trailer$8,000–15,000

Route Survey

Before transport, survey the route for:

  • Bridge weight limits
  • Low overpasses (measure machine height on trailer)
  • Road width restrictions
  • Turning radius at corners and gates
  • Loading dock or ramp capacity at both locations

Reinstallation and Alignment

Foundation Requirements at New Location

  • Verify new floor meets load-bearing requirements (typically 5–10 tons/m²)
  • Check floor flatness: within 3 mm over 3 m for precision machines
  • Update foundation plan if the new location has different soil conditions

Alignment Procedure

  1. Place machine on foundation, leave anchor bolts loose
  2. Rough level using precision level (0.02 mm/m resolution)
  3. Tighten anchor bolts to 50% of specified torque
  4. Fine level: longitudinal and lateral within 0.02 mm/m
  5. Align spindle axis to guideway using test bar and indicator
  6. Tighten anchor bolts to full torque
  7. Verify alignment — readjust if necessary

FAQ

Can I move a deep hole drilling machine myself?

Only for small gun drilling machines under 3 tons. For anything larger, professional rigging is strongly recommended. The cost of one damaged way surface exceeds the rigging contract.

How long does a machine relocation take?

Total project time: 4–8 weeks from planning to production. The actual move (rigging + transport) takes 3–5 days. Reassembly and re-commissioning takes 5–15 days depending on machine complexity.

Does moving a machine void the warranty?

For machines still under warranty, check with the manufacturer. Some require manufacturer-supervised moving. Unauthorised moves may void remaining warranty coverage.

Do I need to recalibrate after moving?

Yes. Even a careful move affects machine geometry. Full recalibration including laser interferometer verification of axis positioning is required. Budget $2,000–5,000 for calibration services.

Should I use the original manufacturer for relocation?

For complex machines under warranty, yes. For older machines out of warranty, a qualified machine tool rigging specialist is sufficient at 40–60% of the manufacturer's cost.


Relocation requirements vary by machine type, size, and distance. Consult the machine manufacturer for model-specific procedures. This article reflects industry practice as of 2026.